Steps for Subcontracting
Production Order System Status
Tell the difference between TECHO and CLOSED.
TECO means Technically completed order, means with out full
completion of order. That production order stopped because of some reasons.
A D V E R T I S E M E N T
CLOSED means after completion of confirmation and settlement the order is fully
closed for further processing.
How to delete released production orders?
In the prodcution order, select Functions --> Deletion flag
-->Active to delete production order. This method can be used for production
orders having CRTD (ie created) and REL (released) status. However, it is not
possible to delete a production order with REL and GMPS (ie. after the withdrawl
of materials for the order) status.
You can TECO the production orders with REL and GMPS status.
CO13 is used to cancel the confirmation of a production
order.
Once Final Goods Receipt is post & Order is completed n it
is Technically Completed it should not allow any goods movement against that
order but this is not happening & one can issue goods even if the order is TECO.
When order status is Teco, system allow us to do the posting
against the order. Once order status is closed, then only order treated as
closed for execution.
In TECO status you can post the remaining activity/goods
movement. Like if you have one order that contains the 5 operation and out of 5,
3 you are confirming in the current period and suppose, rest you are doing in
the next period. So at the time of settlement for current period, order status
should be Teco cause you will do some operation is the next period and cost for
next period should be settle on next period. after that you have to close the
order.
So TECO allows the postings.
If the requirement is not allowing any goods movement while
system status TECO is active, pls try this approach in the config:
1. go to tcode BS22 (Maintain: System Status)
2. look for the system status TECO.
3. Double click the field "TECO".
4. in the transaction control tab look for the business transaction "RMWA" or
goods movement (you can type it in the lower left corner buttom box).
5. select the radio button from "Allowed" to Disallowed".
6. save your changes
|