Difference between MRP vs MPS
Difference between MRP vs MPS
Explain the difference between MRP & MPS. Though both
components gives you the requirement list, what we gain out of MPS run rather
than running MRP. What is the main idea behind this?
A D V E R T I S E M E N T
The following might help in explaining the difference between
MPS and its counter part MRP.
Master Production Schedule (MPS) :
MPS operates within only one level of the BOM, While MRP can be utilized
throughout all levels of a material�s BOM. If a MPS is run on a material, the
necessary orders are planned at that level. Dependent requirements (if any) are
placed on the next BOM level down, and then the process stops.
Main Idea : Master production scheduling (MPS) is a form of
MRP that concentrates planning on the parts or products that have the great
influence on company profits or which dominate the entire production process by
taking critical resources. These items are marked as �A� parts (MPS items) and
are planned with extra attention. These items are selected for a separate MPS
run that takes place before the MRP run. The MPS run is conducted without a BOM
explosion so that the MRP controller can ensure that the Master schedule items (MSI)
are correctly planned before the detailed MRP run takes place.
The master production schedule is a line on the master
schedule grid that reflects the anticipated build schedule for those items
assigned to the master scheduler. The master scheduler maintains this schedule,
and in turn, it becomes a set of planning numbers that drives material
requirements planning. It represents what the company plans to produce expressed
in specific configurations, quantities, and dates. The master production
schedule is not a sales item forecast that represents a statement of demand. The
master production schedule must take into account the forecast, the production
plan, and other important considerations such as backlog, availability of
material, availability of capacity, and management policies and goals. Syn:
master schedule.
Material Requirements Planning (MRP) :
A set of techniques that uses bill of material data, inventory data, and the
master production schedule to calculate requirements for materials. It makes
recommendations to release replenishment orders for material. Further, because
it is time-phased, it makes recommendations to reschedule open orders when due
dates and need dates are not in phase. Time-phased MRP begins with the items
listed on the MPS and determines
(1) the quantity of all components and materials required to
fabricate those items and
(2) the date that the components and material are required.
Time-phased MRP is accomplished by exploding the bill of material, adjusting for
inventory quantities on hand or on order, and offsetting the net requirements by
the appropriate lead times.
MRP Interview Questions:
What is the need of mrp list if stock requirement list is
already there?
The MRP list displays the result of the last planning run.
Changes that have occurred between planning runs are ignored in the MRP list.
In contrast to this, the system displays all changes in stock, receipts and
issues, which have currently occurred, in the stock/requirements list.
Which tcode are used to run MRP?
- MD01 is generally used to run the MRP for all the materials
in a plant normally just before go-live.
- MD02 is used to run MRP for materials which have a BOM i.e multi-level.
- MD03 is used to run MRP for materials which do not have a BOM i.e single
level.
|