The "Packing Process" with an Example
The "Packing Process" with an Example
Example:
You created a order for a material(R-1160 - hard disks) for a qty - 120 pieces.
A D V E R T I S E M E N T
You need to create a delivery and
A)pack 40 pieces each of the material are grouped together into larger cardboard
boxes (PK-100 - shipping/packing material) and
B)these 3 cardboard boxes are put into pallet (PK-095).
Solution:
A)Packing 40 pieces each of material (40 x 3 = 120 pieces)
1)Goto [VL02N] to change the delivery, you already created.
Or you can do the following steps while you are creating a delivery also.
2)Go to "pack" icon.
3)In the upper section, enter the "packing material" (PK-100)
4)In the lower section, change the "partial quantity" to 40 of material R-1160.
5)Select both the lines of upper section and lower section and click the green
ok. It generates a shipping unit/handling unit number.
6)Now, select both lines of upper & lower section & click the button "per part.
qty" (New HU per part qty of material)
Check: click "General Overview" icon to see whether it packed 40 pieces of
material in 3 cartons.
B)Packing all 3 cartons in one big carton(PK-095)
1) from above screen, click "pack HUs" (pack shipping unit)
2)enter the packaging material (PK-095) in the upper section and select this
line.
3)select 3 lines of PK-100 in lower section since you want to pack them in
PK-095.
4)selecting both lines, click "pack" icon.
5)Now all the 3 cartons(PK-100 with 40 pieces each of material) are packed in
one big carton (PK-095).
Check: "General overview" icon.
|